Trillion yuan investment, TSMC wants to build a factory in Taiwan Zhongke
Dec 28,2021
Taichung Mayor Lu Xiuyan revealed yesterday (27) that TSMC has formally proposed a plant expansion plan for Zhongke, and "relevant planning is being processed." It is understood that TSMC has locked the Taichung Golf Course next to the China Science Park with a plant area of nearly 100 hectares and a total investment of 800 billion to 1 trillion yuan.This is TSMC's plan to expand the plant, and the total investment amount has been disclosed for the first time. TSMC’s supply chain revealed that with an investment scale of 1 trillion yuan and a land area of nearly 100 hectares, TSMC will not only plan a 2-nanometer plant in Zhongke, but also a subsequent 1-nanometer plant.

TSMC has invested heavily and once again declared that its process technology is leading, but the legal person is also worried that behind the huge investment amount will be a huge depreciation expense. How to quickly increase the yield rate and reduce the impact of depreciation on gross profit margin and profit will test the management team.
Since TSMC has previously released the message that the 2nm expansion is prioritized by Bamboo Branch Baoshan, Taichung is "grabbing relatives" midway, and the industry is paying great attention. TSMC did not comment on the investment in Zhongke yesterday. TSMC Chairman Liu Deyin has publicly stated that he hopes that TSMC will have a balanced layout in North, Central and South, and each of its production capacity will account for one-third of each. If the Hsinchu 2nm base is not enough, it will evaluate the production capacity in Taichung.
The supply chain revealed that although TSMC’s Zhukebaoshan expansion of the 2 nanometer plant has passed the environmental assessment, the local land environment is relatively complicated, and subsequent acquisition of land still needs to be resolved; the land ownership of the Taichung golf course is simple, and once the negotiation with the landlord Xingnong Group is completed, there may even be subsequent May overtake Zhuke Baoshan's plant construction schedule. It is understood that many members of the Xingnong Group family tend to agree to release the land, but they have not yet reached a consensus.
Due to the huge increase in demand from the global customer base, TSMC's capacity expansion and development can be said to be "five times faster" than in previous years. In order to ensure a steady increase in high-end production capacity, capital expenditures have also been greatly increased, most of which are used for advanced manufacturing processes.
The industry estimates that TSMC’s 2-nanometer trial production will start in 2024 at the earliest, and mass-produce in 2025, and then enter the 1-nanometer, and subsequent generations of "Ami" process. Earlier news broke that TSMC’s Ami-generation process intends to settle in Kaohsiung, but TSMC has not confirmed it.
At present, TSMC's manufacturing process in Zhongke covers 28 nanometers and 7 nanometers. Since 2 nanometer and 1 nanometer process equipment can be shared, the industry speculates that in the future, it will gradually advance from 1.8 nanometers to 1.4 nanometers to 1 nanometers.
The industry expects that in the future, Zhongke is expected to become TSMC's most advanced manufacturing center in the world, and it will play a crucial role for TSMC in its competition with Samsung. Zhongke's turnover this year is expected to exceed the trillion yuan mark, and now that it has increased its investment, Taichung has become a new semiconductor industry center.
The Taichung Golf Course occupies about 90 hectares, and the military shooting range has more than 9 hectares. The Ministry of Science and Technology estimates that the land will be funded about 23.8 billion yuan. According to TSMC’s preliminary plan, Zhongke’s expansion plant hopes to complete the acquisition of land and start EIA-related operations next year. The Taichung City Government expects that after TSMC’s establishment, it is expected to create 7,000 to 8,000 job opportunities.
Since TSMC has previously released the message that the 2nm expansion is prioritized by Bamboo Branch Baoshan, Taichung is "grabbing relatives" midway, and the industry is paying great attention. TSMC did not comment on the investment in Zhongke yesterday. TSMC Chairman Liu Deyin has publicly stated that he hopes that TSMC will have a balanced layout in North, Central and South, and each of its production capacity will account for one-third of each. If the Hsinchu 2nm base is not enough, it will evaluate the production capacity in Taichung.
The supply chain revealed that although TSMC’s Zhukebaoshan expansion of the 2 nanometer plant has passed the environmental assessment, the local land environment is relatively complicated, and subsequent acquisition of land still needs to be resolved; the land ownership of the Taichung golf course is simple, and once the negotiation with the landlord Xingnong Group is completed, there may even be subsequent May overtake Zhuke Baoshan's plant construction schedule. It is understood that many members of the Xingnong Group family tend to agree to release the land, but they have not yet reached a consensus.
Due to the huge increase in demand from the global customer base, TSMC's capacity expansion and development can be said to be "five times faster" than in previous years. In order to ensure a steady increase in high-end production capacity, capital expenditures have also been greatly increased, most of which are used for advanced manufacturing processes.
The industry estimates that TSMC’s 2-nanometer trial production will start in 2024 at the earliest, and mass-produce in 2025, and then enter the 1-nanometer, and subsequent generations of "Ami" process. Earlier news broke that TSMC’s Ami-generation process intends to settle in Kaohsiung, but TSMC has not confirmed it.
At present, TSMC's manufacturing process in Zhongke covers 28 nanometers and 7 nanometers. Since 2 nanometer and 1 nanometer process equipment can be shared, the industry speculates that in the future, it will gradually advance from 1.8 nanometers to 1.4 nanometers to 1 nanometers.
The industry expects that in the future, Zhongke is expected to become TSMC's most advanced manufacturing center in the world, and it will play a crucial role for TSMC in its competition with Samsung. Zhongke's turnover this year is expected to exceed the trillion yuan mark, and now that it has increased its investment, Taichung has become a new semiconductor industry center.
The Taichung Golf Course occupies about 90 hectares, and the military shooting range has more than 9 hectares. The Ministry of Science and Technology estimates that the land will be funded about 23.8 billion yuan. According to TSMC’s preliminary plan, Zhongke’s expansion plant hopes to complete the acquisition of land and start EIA-related operations next year. The Taichung City Government expects that after TSMC’s establishment, it is expected to create 7,000 to 8,000 job opportunities.